Prince2 header
products page

PRINCE2 2009 - Plans part 8

Plans defined

Exception Plans

An Exception Plan is a plan prepared for the appropriate management level to show the actions required to recover from the effect of a tolerance deviation.
If approved, the Exception Plan will replace the plan that is in exception and it will become the new baselined Project Plan or current Stage Plan, as appropriate.

If a Stage Plan is being replaced, this needs the approval of the Project Board.
Replacement of a Project Plan should be referred by the Project Board to corporate or programme management if it is beyond the authority of the Project Board.

An Exception Plan is prepared to the same level of detail as the plan it replaces.
It picks up from the current plan actuals and continues to the end of that plan.
Exception Plans are not produced for Work Packages.
Should a Team Manager forecast that the assigned Work Package may exceed tolerances, they will notify the Project Manager by raising an issue.
If the issue relating to the Work Package can be resolved within stage tolerances, the Project Manager will take corrective action by updating the Work Package or issuing a new Work Package(s) and instructing the Team Manager(s) accordingly.

For more explanation of the types and the use of tolerance in PRINCE2®, see the section covering ‘Progress’.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.

This product contains EVERYTHING in the publications:

Managing Successful Projects with PRINCE2 - 2005 edition
Managing successful Projects with PRINCE2 – 2009 edition
Directing Projects with PRINCE2.
plus:
The Complete Project Management package.

And much more besides - at a fantastic price.