Prince2 header
products page

PRINCE2 2009 - Progress part 17

The PRINCE2® approach

Event-driven and time-driven controls

Reporting progress

The frequency of reporting should reflect the level of control required, and this is likely to vary during the project.
For example:

During the design stage, less frequent control may be required than during later management stages If the team is highly experienced then less frequent reporting may be appropriate, whereas for an inexperienced team the Project Manager may wish to increase the frequency of reporting until sufficient confidence has been gained on the capability of the team

The following management products are used for progress reporting:

Checkpoint Report

The Team Manager will produce this to provide the Project Manager with details of progress against the Work Package.
The Work Package will include the frequency of Checkpoint Reports required.
The Project Manager will collate Checkpoint Reports and use these as part of the progress assessment when reviewing stage status

Highlight Report

The Project Manager produces this report on management stage progress for the Project Board.
The Project Board will determine the frequency of Highlight Reports required, either for the whole project or stage by stage, and document this in the Communication Management Strategy.
The Highlight Report allows members of the Project Board to manage by exception between end stage assessments as they are aware of the tolerances agreed with the Project Manager in the Stage Plan.
The Highlight Report should confirm that progress is being made within these tolerances and provide early warning of possible problems which may need actions.
As part of the Communication Management Strategy, the Project Board can request that copies of the Highlight Report be sent to other interested parties outside the project.
The Project Board may also issue the Highlight Report (or a summary of it) to corporate or programme management.

End Stage Report

This is produced by the Project Manager towards the end of each management stage, providing the Project Board with the information on the progress to date, the overall project situation and (in tandem with the next Stage Plan) sufficient information to ask for a Project Board decision on what to do next with the project.

End Project Report

This is produced by the Project Manager towards the end of the project, during the Closing a Project process, and is used by the Project Board to evaluate the project and authorize closure.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.

This product contains EVERYTHING in the publications:

Managing Successful Projects with PRINCE2 - 2005 edition
Managing successful Projects with PRINCE2 – 2009 edition
Directing Projects with PRINCE2.
plus:
The Complete Project Management package.

And much more besides - at a fantastic price.