Activities
Review Work Package status
This activity provides the means for a regular assessment of the status of the Work Package(s).
The frequency and formality of this activity will usually be aligned with the frequency of reporting defined in the Work Package(s) and supported by the Stage Plan for the current stage.
Diagram 1 shows the inputs to, and outputs from, this activity.
© Crown copyright 2005 Reproduced under licence from OGC
Diagram 1
PRINCE2® recommends the following actions for each Work Package in progress:
- Collect and review progress information from the Checkpoint Report for the Work Package being executed:
- Assess the estimated time and effort to complete any unfinished work (including that not yet started)
- Review the Team Plan with the Team Manager (or the milestone extract from it if the commercial environment means it is inappropriate for the Project Manager to see its contents) to ascertain whether work will be completed on time and to budget
- Review entries in the Quality Register to understand the current status of quality management activities
- Confirm that the Configuration Item Record for each product in the Work Package matches its status
- If necessary, update the Risk Register and Issue Register
- Update the Stage Plan for the current stage with actuals to date, forecasts and adjustments.
Diagram 2 shows the responsibilities for this activity.
© Crown copyright 2005 Reproduced under licence from OGC
Diagram 2
PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.
This product contains EVERYTHING in the publications:
Managing Successful Projects with PRINCE2 - 2005 edition
Managing successful Projects with PRINCE2 – 2009 edition
Directing Projects with PRINCE2.
plus:
The Complete Project Management package.
And much more besides - at a fantastic price.