PRINCE2 2009 - Managing a Stage Boundary part 6

Activities

Update the Project Plan

The Project Board uses the Project Plan throughout the project to measure progress.

The Project Plan is updated to incorporate actual progress from the stage that is finishing, and to include forecast duration and costs from the Exception Plan or Stage Plan for the stage about to begin.

Details of any revised costs or end dates are used when updating the Business Case.

See the section covering ‘Plans’ for more details on planning.

Diagram 1 shows the inputs to, and outputs from, this activity.

Managing a Stage Boundary project plan diagram 1 smallManaging a Stage Boundary project plan diagram 1

Diagram 1

PRINCE2® recommends the following actions:

  • Check that the current Stage Plan is up to date with actual progress and update if necessary
  • Revise the Project Plan to reflect:
    • Actuals from the current Stage Plan
    • Forecasts from the next Stage Plan, or the impact of the Exception Plan
    • Any changes to the Project Product Description
    • The implications of any issues or risks
    • Any new or changed PRINCE2 process-tailoring requirements for the project
    • Any changed or extra products sanctioned by the Project Board
    • Any changes within the Project Initiation Documentation (e.g. revised project approach, strategies, project controls, project management team structure or role descriptions)
  • Update the Issue Register and Risk Register if any new issues or risks have been identified (or if existing ones need to be modified).

Diagram 2 shows the responsibilities for this activity.

Managing a Stage Boundary project plan diagram 2 smallManaging a Stage Boundary project plan diagram 2

Diagram 2

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.

This product contains EVERYTHING in the publications:

Managing Successful Projects with PRINCE2 - 2005 edition
Managing successful Projects with PRINCE2 – 2009 edition
Directing Projects with PRINCE2.
plus:
The Complete Project Management package.

And much more besides - at a fantastic price.