Tailoring PRINCE2® to the project environment

Commercial customer/supplier environment

Themes

Risk

In a commercial context there may be a need for more than one Risk Register as some project risks could be unique to only one party, with good reasons for them not to be visible to the other party.
Where a joint Risk Register is used, care should be taken as to whose risk it really is, and the risk owner appointed accordingly.

For example, on a fixed-price contract any cost overruns will impact the supplier’s Business Case, but timescale overruns will typically impact mostly the customer’s Business Case.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.

This product contains EVERYTHING in the publications:

Managing Successful Projects with PRINCE2 - 2005 edition
Managing successful Projects with PRINCE2 – 2009 edition
Directing Projects with PRINCE2.
plus:
The Complete Project Management package.

And much more besides - at a fantastic price.