Change will occur in any project. Particular changes can have a large detrimental affect on a project unless carried out in a controlled manner.
For any item change is not inevitable as the process of change must be judged against certain criteria.
These might be:
It might be that management decides not to proceed with the change following such an assessment.
All approved changes must be accounted for in the schedules and budget as necessary.
Change control can be used to capture a wide range of Project Issues which may include:
The project team must decide, with the approval of the Project Board what items come under change control.
Methods used to control change are given in ‘Change control technique’.
All Project Issues must be captured, logged and categorised.
These may arise at any time and from anyone with an interest in the project.
Project Issues are not only negative but may be those having a positive impact on the project.
These may be:
Legislative change
Corporate change in direction
New customer
New supplier
Changes in project management team membership
Competitor activity
Directive from programme management
Corporate reorganisation
The management of Project Issues will involve:
As Project Issues can come form almost any source it is important to have a good process that will capture and assess their impact.
Project Issues can result in in two forms of change:
A Request for ChangeThis will result in a change to the specification or Acceptance Criteria of the project or one of its products.
Any additional costs would normally be funded by the Customer.
This covers errors or omissions found in completed work or planned for the future.
Either situation will result in agreed Acceptance Criteria not being met.
Costs will normally be funded by the supplier involved.
Note that any such costs for suppliers should be agreed in their contracts.
These should include responsibilities and any arbitration processes.
Any new risks will need to be assessed for their impact (as part of Examining Project Issues (CS4).
Any measures that may require implementing should be approved by the Project Board if a major change to the project is anticipated.
Someone (or body) must have the responsibility to authorise change.
It will depend upon the nature of the change and the potential impact on the project.
The Project Board will have signed off on the project expecting a particular product and scope.
If any changes will affect this the Project Board should authorise any changes.
This would be suitable if only a few changes were anticipated.
Most projects have a lot of changes which would tie up the time of the Project Board.
The level of authorisation should be discussed and agreed during project initiation.
The key is to decide which Project Issues should be authorised by the Project Board and at what level of impact.
Others can be authorised by, say the Project Manager or to a group (called ‘change authority’), if agreed by the Project Board.
This is a vital aspect of project control and project success and nay authority should be identified in appropriate job descriptions.
Any projects that form part of a programme will be advised by programme management of the level of authority given to the Project Board.
The Project Board must consider:
It may be better to allocate a budget to the ‘change authority’ to improve efficiency. This will reduce the time spent by the Project Board on minor changes that may be frequent. The amount of any budget, the responsibilities, how it is used and any other constraints must be defined and agreed.
In addition, the Project Board may set a limit in the budget for the cost of implementing any one change and a limit to expenditure for any particular stage.
The ‘change authority’ may in fact be given to those individuals with delegated Project Assurance responsibilities.
All Project Issues should be assessed against any impact on the Business Case.
Project issues should be assessed for risk impact.
All changes must be balanced against the advantage of implementation versus the time, cost and risk in carrying it out.
All change control procedures must be consistent with any used by a higher level programme.
All changes must consider the impact on such programmes as well as possible impact on other projects or areas outside of the programme.
Change control and configuration management should be consistent with each others approach.
This should be identified in the Configuration Management Plan.
During a project there may be many opportunities that are identified that could improve costs and performance.
These may not result in actual changes in a current project but should be noted as a Project Issue.
These would then be recorded in the Lessons Learned Log.