The PRINCE2® approach
The contents
Timescale
Corporate and/or programme management will wish to know:
- Over what period the project costs will be incurred
- Over what period the cost/benefits analysis will be based
- When the organization can expect to accrue benefits
- What the earliest/latest feasible start date is
- What the earliest/latest feasible completion date is.
Identifying the timescale requirement for a project can help identify tolerances and timings for benefits reviews.
PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.
This product contains EVERYTHING in the publications:
Managing Successful Projects with PRINCE2 - 2005 edition
Managing successful Projects with PRINCE2 – 2009 edition
Directing Projects with PRINCE2.
plus:
The Complete Project Management package.
And much more besides - at a fantastic price.