© Crown copyright 2009 All rights reserved. Material is reproduced with the permission
of the Cabinet Office under delegated authority from the Controller of HMSO.
Activities
Prepare premature closure
In some situations, the Project Board may have instructed the Project Manager to close the project prematurely.
In such circumstances, the Project Manager must ensure that work in progress is not simply abandoned, but that the project salvages anything of value created to date and checks that any gaps left by the cancellation of the project are raised to corporate or programme management.
Diagram 1 shows the inputs to, and outputs from, this activity.
© Crown copyright 2005 Reproduced under licence from OGC
Diagram 1
PRINCE2® recommends the following actions:
- Update the Issue Register (and, if necessary, the Issue Report) to record the premature closure request
- Update the Project Plan with actuals from the final stage
- Request a Product Status Account from Project Support. From this, determine which of the project’s products:
- Have been approved by the authorities identified in their Product Descriptions
- Are currently in development (and which of those need to be completed)
- Are covered by approved concessions
- Have yet to be started
- Need to be made safe
- May be useful to other projects
- Agree the means for recovering products that have been completed or are in progress (if appropriate). This will need Project Board consultation and may include additional work to create, make safe or complete products that might be useful to other projects (for example, making a part-built building safe and weatherproof). In some cases, the additional work may require an Exception Plan
- Seek approval to give notice to corporate or programme management that resources can be (or are about to be) released early
Diagram 2 shows the responsibilities for this activity.
© Crown copyright 2005 Reproduced under licence from OGC
Diagram 2
PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.
This product contains EVERYTHING in the publications:
Managing Successful Projects with PRINCE2 - 2005 edition
Managing successful Projects with PRINCE2 – 2009 edition
Directing Projects with PRINCE2.
plus:
The Complete Project Management package.
And much more besides - at a fantastic price.