Prince2 header
products page

PRINCE2 2009 - Change part 10

The PRINCE2 approach

Establish controls

Daily Log

A Daily Log is used to record problems/concerns that can be handled by the Project Manager informally.
Issues initially captured on the Daily Log may later be transferred to the Issue Register if, after examining them, it is decided they need to be treated more formally.

The Daily Log can also be used to record required actions or significant events not caught by other PRINCE2® registers and logs.
It acts as the project diary.

For the Product Description of a Daily Log see the folder ‘Product Description outlines’ as part of the product package.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.

This product contains EVERYTHING in the publications:

Managing Successful Projects with PRINCE2 - 2005 edition
Managing successful Projects with PRINCE2 – 2009 edition
Directing Projects with PRINCE2.
plus:
The Complete Project Management package.

And much more besides - at a fantastic price.