A stage should not exceed the tolerances agreed with the Project Board.
The Project Manager can only take corrective action or maintain the status quo as long as the stage (or project) is forecast to be completed within the tolerances set by the Project Board.
This activity applies where any corrective action within the Project Manager’s control would not save the stage (or project) from going beyond the tolerances agreed.
This applies to all types of issue and risk (or aggregation of them) that cannot be resolved within the tolerances set by the Project Board.
As it may take some time to gather the information to create an Exception Report, it is recommended that the Project Board be alerted as early as possible.
Therefore, the Project Manager may wish to execute this activity in two steps: an early notification to the Project Board of the forecast exception situation in order to prepare them, followed by supporting information in the form of an Exception Report.
The Project Manager should execute any decision by the Project Board in response to the escalation.
Escalating issues and risks is good practice and should not be seen as failure.
The earlier that issues are escalated, the more time [see 'The Complete Time Management package'] is available to implement any corrective actions.
For more details on management of risk, see the section covering ‘Risk’.
For more details on issue and change control, see the section covering ‘Change’.
For more details on exception management, see the section covering ‘Progress’.
Diagram 1 shows the inputs to, and outputs from, this activity.
Diagram 1
PRINCE2® recommends the following actions:
Diagram 2 shows the responsibilities for this activity.
Diagram 2
PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.