This shows the cumulative probability graph for tasks ‘A’ or ‘B’ and tasks ‘A’ and ‘B’ combined [see The Risk Management process - Evaluate - independent correlation]. Note that although we were looking at values of:
Delay | Probability |
---|---|
7 | 0.3 |
9 | 0.5 |
11 | 0.2 |
We are actually seeing the ranges:
Delay | Probability |
---|---|
6 to 8 | 0.3 |
8 to 10 | 0.5 |
10 to 12 | 0.2 |
Delay | Calculation | Probability | ||||
---|---|---|---|---|---|---|
14 | 0.3 x 0.3 | 0.09 | ||||
16 | 0.3 x 0.5 | + | 0.5 x 0.3 | 0.30 | ||
18 | 0.3 x 0.2 | + | 0.5 x 0.5 | + | 0.2 x 0.3 | 0.37 |
20 | 0.5 x 0.2 | + | 0.2 x 0.5 | 0.20 | ||
22 | 0.2 x 0.2 | 0.04 |