Introduction
The Risk Management process
Risk issues
Modelling
Events
Networks and branching
Other
Cost | |
A | 5 |
B | 5 |
C | 5 |
D | 5 |
E | 5 |
F | 5 |
G | 5 |
H | 5 |
Total | 40 |
The model shows 8 activities, ‘A’ to ‘H’. Each has a cost of 5 units.
If we know with absolute certainty that each cost is 5 then the total cost must be 8 x 5 = 40.
This is the very simplest model.
Creating models for risk assessment is not as tricky as you might think. The mathematics is quite straight forward (for the simpler models) and, for the most part, many businesses carry this out to some degree using spreadsheets etc. For example, most businesses will be looking to forecast costs for the new financial year.
This will based upon many items, for example:
In the simple model above we have 8 activities ‘A’ to ‘H’ with no uncertainty.
We may assess the same scenario with a degree of uncertainty [see Cost model].
other areas of interest in the series
© Copyright 2020 all rights reserved March Limited