Authorize initiation
Summary
PRINCE2® requires that Project Board members undertake the following responsibilities collectively for authorizing initiation.
Actions required for authorizing initiationReview and approve the Project Brief:
- Confirm the project definition and approach
- Review and approve the Project Product Description
- Formally confirm the appointments to the core project management team
- Review and approve the outline Business Case, particularly the projected business benefits
Approve the Initiation Stage Plan:
- Approve the plan to develop the Project Initiation Documentation
- Obtain or commit the resources needed by the Stage Plan for the initiation stage
- Ensure that adequate reporting and control mechanisms are in place for the initiation stage
- Set tolerances for the initiation stage
- Request the necessary logistical support (for example accommodation, communication facilities, equipment and any Project Support) from corporate or programme management
- Understand any risks that affect the decision to authorize initiation
- Confirm to the Project Manager that the work defined in the Initiation Stage Plan may start
Communicate:
- Keep stakeholders (corporate or programme management and other interested parties) informed about project progress by issuing a project initiation notification
All references above are in Directing Successful Projects with PRINCE2 unless stated otherwise.
PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.
This product contains EVERYTHING in the publications:
Managing Successful Projects with PRINCE2 - 2005 edition
Managing successful Projects with PRINCE2 – 2009 edition
Directing Projects with PRINCE2.
plus:
The Complete Project Management package.
And much more besides - at a fantastic price.