The Project Board is likely to receive a number of requests for advice from the Project Manager, covering:
Formal requests will be raised in the form of an Issue Report.
The composition for an Issue Report can be found in the folder ‘Product Description outlines’ as part of the product description - but it essentially documents the cause, impact, options and recommendation for dealing with the request.
Shown below under Request:, Project Board (or Change Authority) response: and Considerations:
Request:
Request for changeProject Board (or Change Authority) response:
Considerations:
If a request for change involves extra cost, there are three principal ways to fund it:
Tolerance should not be used to fund requests for change.
Request:
Off-specificationConsiderations:
Request:
Problem/concernConsiderations:
Could the problem/concern be resolved by relaxing the stage tolerances?
Resource issues, in particular, frequently have to be escalated to Project Board members.
Committing resources is a key Project Board duty.
The Project Manager should be expected to provide adequate notice of resource requirements and to negotiate the resourcing needs and timing in the course of planning.
However, if the agreed resources are not then made available according to plan, progress may be affected quickly and seriously.
In these circumstances, the intervention of Project Board members inevitably carries more weight than the Project Manager’s efforts.
Project Board members should be generally receptive to informal requests for direction.
However, the nature and frequency of the requests can provide indications of strengths and weaknesses at the project management level.
Project Board members should expect frequent requests whenever plans are being prepared, but if requests continue to arise after the plan is approved, look for clues:
Anything that may have a significant impact on the plan should be recorded as a risk, problem/concern, request for change or off-specification - is this happening? If so, are the issues really important or just trivia? If not, is the Project Manager maintaining adequate change control/Risk Management? [see ‘The Complete Risk Management package’]
Are the Project Assurance arrangements adequate/appropriate? Should the Project Board delegate more or less authority to the Project Manager and/or to Project Assurance? Or should the manager set up a working level Change Authority?
Many issues do need to be escalated to the Project Board, e.g. any significant changes to scope, approach, products, budgets or schedules.
If the requests are reasonable and there is evidence that the plans and project management disciplines are operating adequately, Project Board members can respond with appropriate guidance and help - and be reassured that the day-to-day management is secure.
However, if the clues point to project management weaknesses, Project Board members may need to drill down further - or direct Project Assurance Efforts - to check on the adequacy of plans and the application of controls and to identify and resolve the weaknesses.