Prince2 header
products page

PRINCE2 2009 - Directing Projects with PRINCE2 part 65

Authorize project closure

Summary

PRINCE2® requires that Project Board members undertake the following responsibilities collectively for authorizing project closure.



Actions required for authorizing project closure

Confirm handover and acceptance:

  • Verify that the handover of the project product was in accordance with the Configuration Management Strategy and in particular that records of all required user acceptance and operational/maintenance acceptance exist
  • Ensure that, where appropriate, the resulting changes in the business are supported and sustainable
  • Ensure that any customer quality expectations that cannot be validated until after the project closes (e.g. performance levels regarding reliability) are included in the Benefits Review Plan as a post-project check

Approve the End Project Report:

  • The version of the Project Initiation Documentation which was approved at project initiation should be used as the baseline to assess how the project has deviated from its initial basis, and to provide information against which the success of the project can be judged
  • Ensure follow-on action recommendations have been recorded correctly in the End Project Report and that the appropriate groups have been made aware of their responsibility for taking them forward
  • Approve the End Project Report for distribution to stakeholders, for example corporate or programme management
  • Review the Lessons Report and agree who should receive it. Ensure that the appropriate groups (for example corporate or programme management, or a centre of excellence) have been made aware of their responsibility for taking any recommendations forward

Confirm the Business Case:

  • Confirm the updated Business Case by comparing actual and forecast benefits, costs and risks against the Business Case approved with the Project Initiation Documentation (it may not be possible to validate all the benefits as some will not be realized until after the project is closed)

Approve the Benefits Review Plan:

  • Review and gain approval for the updated Benefits Review Plan, ensuring that it addresses the expected benefits that cannot yet be validated
  • As the Benefits Review Plan includes resources beyond the life of the project, responsibility for this plan needs to transfer to corporate or programme management

Issue the project closure notification:

  • Review and issue a project closure notification in accordance with the Communication Management Strategy
  • Advise those who have provided the support infrastructure and resources for the project that these can now be withdrawn
  • Release the resources provided to the project
  • Provide a closing date for costs being charged to the project

All references above are in Directing Successful Projects with PRINCE2 unless stated otherwise.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.

This product contains EVERYTHING in the publications:

Managing Successful Projects with PRINCE2 - 2005 edition
Managing successful Projects with PRINCE2 – 2009 edition
Directing Projects with PRINCE2.
plus:
The Complete Project Management package.

And much more besides - at a fantastic price.